Trans-Canada Highway east of Golden to close for 5 days after Easter weekend - Action News
Home WebMail Friday, November 22, 2024, 08:02 PM | Calgary | -11.3°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
British Columbia

Trans-Canada Highway east of Golden to close for 5 days after Easter weekend

The Trans-Canada Highway between Golden, B.C., and Castle Junction in Alberta will be closed for five days starting April 11 as contractors continue work on the Kicking Horse Canyon project.

Detour via highways 93S and 95 could add up to 1 hours travel time, B.C. ministry says

The construction will improve a four-kilometre stretch of highway through Kicking Horse Canyon east of Golden, B.C.  pictured here.
The construction will improve a 4.8-kilometre stretch of highway through Kicking Horse Canyon east of Golden, B.C., pictured here. (Government of B.C.)

The Trans-Canada Highway between Golden, B.C., and Castle Junction in Alberta will be closed for five days starting April 11 as contractors continue work on the Kicking Horse Canyon project.

B.C.'s Ministry of Transportation and Infrastructure says the closure is scheduled to begin at noon on April 11 and lastuntil 11:59 p.m. on April 15.

Drivers will be rerouted to highways 93S and 95, which could add up to 1hours of travel time. Comingjust after the Easter long weekend, the closure could affect those who intend to extend their long weekend beyond Easter Monday.

In a media release, the ministry says the closure is "necessary" and that there will be roadside signs up in advance to let drivers know of the alternativeroute.

It says the area will be opened twice a day for local trafficthat has prearranged permits, as well as school buses and emergency vehicles.

The area was closed for 32 days last spring, between the Easter and May long weekends. The province says that after this closure, there won't be any full-day closures of Highway 1 in the areauntil fall.

Phase 4 the final phase of the Kicking Horse Canyon project to widen and upgrade the section of Highway 1 between Golden and Yoho National Parkis expected to be complete by winter 2023-24.

More than $600 million is being invested in the project by the B.C. and federalgovernments.