'Ick factor,' not science is driving Victoria's $765M wastewater treatment project, say critics

Two years into the construction of Victoria's first wastewater treatment facility and a year and a half out from completion, the $765 million project is still being debated heralded as long overdue by some and dismissed as unnecessary by others.

Treatment facility has to be up and running by 2020 in order to comply with federal regulations

An aerial view of the construction progress at the site of the new wastewater treatment facility at McLoughlin Point on Vancouver Island. (Submitted/Capital Regional District)

Two years into the construction of Victoria's first wastewater treatment facility and a year and a half out from completion, the $765 million project is still being debated heralded as long overdue by some and dismissed as unnecessary by others.

Wastewater facilities don't typically stoke civic pride, but the project and its decades-long history areunique because most of the Victoria area has never treated its sewage.

"I think it is huge," saidElizabeth Scott, deputy project director of the wastewater treatment facility,located at Victoria's McLoughlin Point on therocky south coast of Vancouver Island.

"There [are] a lot of residents that understand the importance of the project ...and will feel a great deal of pride in the project for generations to come."

Currently, wastewater is screened and anything larger than 6mm is blocked.The rest flows into two separate outfall pipesand is then discharged into the Strait of Juan de Fuca.

The region is the last major coastal community in North America to dispose of untreated sewage into the marine environment, according to the local government.

Several scientists have repeatedly argued that the area's cold water and fast flowing currents mean the wastewater is quickly diluted and produces no harmful effects.

Federal laws changed in 2012

However, federal regulations introduced in 2012mean that the Capital Regional District, which includes Victoria, Saanich, and Esquimalt, B.C., have to have a treatment plant up and running by the end of 2020.

Construction of the facilitybegan in 2017. When it'sfinished, it will include three levels of treatment.Officials say it will be able to remove contaminants that are particularly concerning like pharmaceuticals.

It will also quell the criticism and protest that has been levelled against the region for decades.

Deputy project director Elizabeth Scott says the most challenging part of the wastewater treatment project is that it requires laying as much as 30 kilometres of pipe, which will run through urban areas. (Briar Stewart/ CBC News )

"We have had a false image of a garden cityand underneath, we had all the sewage going into the ocean," saidJames Skwarok, a Victoria teacher who strolled the coasts and streetsdressed as a human turd called Mr.Floatie beginning in 2004.

He got the inspiration for his environmental protest about sewage dumpingfrom a character on the cartoon show South Park.

As the mascot for the group P.O.O.P. (People Opposed to Outfall Pollution), Mr. Floatieraised a stink, becoming a walking, visual representation of a message environmental groups had been delivering for years.

"Our beautiful ocean is not a big magical toilet where everything disappears," Skwarok said."It was an embarrassment for the tourism industry and for local politicians to have this tall turd walking around."

Mr. Floatie and other environmentalists ran a public campaign to try and pressure officials to build a wastewater treatment plant. The mascot frequently spoke to tourists visiting Victoria about where the city's sewage was ending up. (Chat Hipolito/The Canadian Press)

Over the years officials from Washington State havethreatened a tourism boycott of the Victoria area because of the sewage issue.

Once construction began two years ago, Mr. Floatie and local politicians headed to Seattle to make amends. As for the mascot costume, it is now retired and sitting in the Royal BC Museum.

'Ick factor'

While the impact of Mr. Floatie and the protests were successful in helping to get the plant built, scientist Tom Pedersen argues the whole campaign obscured the situation.

"I think the whole issue has been driven by misperception of the public and that's what some of us euphemistically called the ick factor," he said.

James Skwarok, aka Mr. Floatie, was invited to community events, and the mascot briefly ran for mayor of Victoria in 2005. (Briar Stewart/CBC)

Pedersen, who recently retired from the University of Victoria, has held several positions over the years, including Dean of Science, and he served on a marine science panel made up of experts from B.C. and Washington State who studied the sewage issue.

He contends there is no scientific rationale for building the plant because the ocean's strong tidal currents are naturally decomposing what is in the wastewater. He adds it is one of the very few spots in the world where it is safe to dispose of sewage this way.

With construction well underway, Pedersen says he understands that the treatment facility is a done deal, but he suggests that when it comes to marine protection, the $765 million spent on the plant could have been better used elsewhere.

Tom Pedersen recently retired from the University of Victoria but has been studying the sewage issue for years. He says the wastewater treatment facility is unnecessary. (Briar Stewart/CBC News)

When the plant is up and running, it will provide sewage treatment for an area with a population of about 320,000. The facility will treat more than 100 million litres of wastewater each day, and the sewage sludge that is left over willbe pumped to a separate facility where it will be turned into biosolids.

Officials say the hope is to be able to use those to fuel cement kilns.

"The regulations that the federal government put into place gave us a firm deadline," saidColin Plant, board chair for the Capital Regional District.

He saiddebates over the science became moot once those regulations were put into place. He believes many Canadians may be surprised when they learn that the Victoria area hasn't been treating its sewage, considering Vancouver Island has a reputation for being green and environmentally progressive.

"The general public is of the mind now that, thank goodness, we're finally doing the right thing."