Kicking Horse Canyon stretch of Trans-Canada reopens Friday

Albertans heading west into British Columbia this weekend will save at least an hour, as the Kicking Horse Canyon project wraps up ahead of schedule.

2-month construction closure wraps up, saving drivers up to 90 minutes as they travel improved Highway 1

The construction will improve a four-kilometre stretch of highway through Kicking Horse Canyon east of Golden, B.C.  pictured here.
The upgrades to the 4.8-kilometre stretch of Highway 1 through Kicking Horse Canyon east of Golden, B.C., include realigning and widening sections to ease travel and mitigaterock fall and avalanche hazards. (Government of B.C.)

Albertansheading into British Columbia this weekend will save at least an houras they traverse newly completed sections of Highway 1.

The stretch of the Trans-Canada highwayeast of Golden, B.C., will be available to drivers from 6 a.m. MT Friday onward. The portion of the road has been closed for two months, with the exception of Thanksgiving weekend, and was set to reopenDec. 1.

The completed portion oftheKicking Horse Canyon project includes up to two kilometresof the final 4.8-kmsection.

The alternate route had drivers detour between Banff and Lake Louise at Castle Junction on Highway 93, before heading north again at Radium Hot Springs.

The upgrades include widening the highway from two to four lanes, realigning sections, creating more space for cyclists, and work tomitigaterock fall and avalanche hazards.

The fourth and final phase of theKicking Horse Canyon projectis set to be completed by winter 2023-24.

Phase 4 of the Kicking Horse Canyon project is expected to be complete by winter 2023-24. (Submitted by Get Into B.C.)

Overnight closures can be expected through the winter, though no full closures are scheduled for the project until the spring.