Fleuve-Montagne walkway will cost $13M more than expected - Action News
Home WebMail Saturday, November 23, 2024, 03:28 PM | Calgary | -11.6°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Montreal

Fleuve-Montagne walkway will cost $13M more than expected

Montreal has confirmed that the Fleuve-Montagne walkway, meant to celebrate Montreals 375th anniversary, will cost $55.3 million - $13.1 million more than anticipated.

$47M already spent on consulting deal, 3 construction contracts, with 3 left to be awarded

Construction began Monday on McTavish Street and Docteur Penfield Avenue. (CBC)

The City of Montreal has confirmed that the Fleuve-Montagne walkway, meant to celebrate Montreal's 375th anniversary, will cost $55.3 million $13.1 million more than anticipated.

The walkway will run from Mount Royal to the Pointe--CallireMuseum, featuring widened sidewalks, more treesand public art. It was originally slated to cost $42.4 million.

The walkway will run from Mount Royal to the Pointe--Callire museum. It is set to be finished by mid-may. (CBC )

Montreal Mayor Denis Coderre says the bump in price is due to unforeseen underground infrastructure issues.

"I had a report saying that I had to re-do the underground for Sherbrooke [Street], that if I didn't do anything I would have major problems," he said.

'We're not getting bang for our buck'

Projet Montral leader Luc Ferrandez isn't sure the hefty price tag is worth it.

Projet Montral leader Luc Ferrandez says he expects the walkway's price to keep growing: 'We expect that it will easily go up to $60 million.' (CBC)

"We don't get any bang for our buck. This project is going nowhere. Basically, it's sidewalk enlargement in places where it will barely be noticed," he said.

He added that he thinks that the rising cost has more to do with a rushed timeline than underground infrastructure.

"There's some kind of ribbon-cutting fetishism, it has to be [done] in June, and therefore, since it's almost impossible to realize, the costs are going up and up and up," he said.

Ferrandez argues that Fleuve-Montagne's tight deadline led fewercompanies to apply for contracts, driving up the price.

3 contracts left to award

Since May, three construction contracts and one consulting contract have been awarded for work on the walkway, at a total cost of about $47 million.

The city says itstill hasthree more construction contracts to awardto finish the rest of the project.