N.B. Power facing $71M bill for generator troubles at idle nuclear plant - Action News
Home WebMail Friday, November 22, 2024, 09:32 AM | Calgary | -11.8°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
New Brunswick

N.B. Power facing $71M bill for generator troubles at idle nuclear plant

Aproblem in themassive electrical generator at the Point Lepreau nuclear station that has been delaying its return to service will take several more weeks to resolve and cost an expected $71 million in repairs and lost production, N.B. Power estimates.

Utility rejects suggestion Lepreau spending throws 'good money after bad'

A generating station seen from across a body of water
The Point Lepreau Nuclear Generating Station has not operated since the first week in April. A problem in its main generator is expected to prolong its outage until at least Sept. 7. (Marc Godbout/Radio-Canada)

Aproblem in themassive electrical generator at the Point Lepreau nuclear station that has been delaying its return to service will take several more weeks to resolve and cost an expected $71 million in repairs and lost production, N.B. Power estimates.

But the actual problem with the one million horsepower generator, which was discovered nearly a month ago,hasn't been fully diagnosed yet,and the utility warned costs could climb if a fix takes longer than expected.

"You said early September is when you are estimating.Is that sort of a best case scenario?" asked J.D. Irving lawyer Glen Zacher about the Lepreau generator, during N.B. Power's rate hearing on Monday.

"Yes, that would be fair," replied Jason Nouwens, Lepreau's director of regulatory and external affairs.

Nouwens declined to say what a worst case scenario forthe repair might be.

The Lepreauplant has been offline since early April for what was supposed to be a $137 million, three-month maintenanceshutdown.

No work was done on the station's main generator as part of that program, and according to Nouwensthere was no reason to becauseit was operating normally in the spring.

"We do have monitoring on the generator," said Nouwens."Those monitoring systems did not identify that there was an issue and the generator was operating properly when we shut down."

But after sitting idle for three months, the generator showed a problem during routine testing done on all plant equipmentprior to being restarted, Nouwens said, andthere is no alternative but to keep Lepreau idle until the malfunction is fully diagnosed and repaired.

Company's name on the side of a stone building.
N.B. Power is seeking approval to raise rates in some cases by 20 per cent over two years to help with its ongoing financial problems. (Michael Heenan/CBC)

"It has to be remedied now," he said.

Nouwens said engineers at the plant believe they have traced the problem to what he said was a single "stator bar" in the generator but they still do not know how or why the malfunction occurred.

Currently the generator is being disassembled to retrieve and replace the defective piece and to investigate what caused it to stop working properly.

Once the engineers are satisfiedthey fully understand what happened, the generator will be piecedback together and the station will be restarted sometime around Sept. 7. However, that will dependon the puzzling failure being completely resolved.

The problemcomes at a difficulttime for the financially-batteredutility.

More than a decade of equipment failures and disappointing performance at the nuclear plant has left N.B. Power more than $5.3 billion in debt, with multi-billion dollar capital projects on its horizon.

power plant with four large, red-and-white stacks extending into the air with a bright blue sky in the background.
The Bayside natural gas generating station, right, is supposed to be undergoing an extensive maintenance outage to prepare for winter production, but has had to keep operating to compensate for problems at N.B. Power's nuclear plant. (Robert Jones/CBC)

N.B. Power is currently in the process of askingthe New Brunswick Energy and Utilities Board to raise rates by an average of 19.4 per cent over two years to begin fixing its financialproblems. That would mean rates rise9.25 per cent this year and another 9.25 per cent beginning next April.

Proposed increases to residentialand large industrial customers are even higher, totalling 20.6 per cent over the two years.

The shutdown at Lepreau is also havingcascading effects throughout the utility.

Planned maintenanceoutages N.B. Power's thermal generating stations in Belledune and Bayside to prepare them for the winter have both had to be delayed while they compensate for Lepreau being idle for more than five months.

A bald man in a grey suit sits at a table behind a microphone and writes on a piece of paper.
Energy and Utilities Board member Christopher Stewart is presiding over a three-person panel that is evaluating N.B. Power's request for two years of large rate increases. (Pat Richard/CBC)

Zacher asked the utility if it has evaluated whether Lepreau's troubles outweigh its advantages or whether it is "all in" on supporting the nuclear plant, whateverthe cost.

"At what point do you reach the inflection point where you consider yourself throwing good money after bad?"asked Zacher.

Utility officials said despite its problems, the nuclear plant is a net benefit.

"While we have not seen the performance that we would ideally like with the amount we have spent in the past, we still have seen benefitsfrom the operation of Point Lepreau," said N.B. Power's Craig Church.

"When that unit is running it is producing energy at a rate that is much lower than the alternatives that we have."