NB Power seeks to repay Lepreau bill over 27 years - Action News
Home WebMail Saturday, November 23, 2024, 04:41 PM | Calgary | -11.6°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
New Brunswick

NB Power seeks to repay Lepreau bill over 27 years

NB Power might need to be more aggressive in paying off deferred costs from the refurbishment of its Point Lepreau Nuclear Generating Station, the New Brunswick Energy and Utilities Board heard Monday.

Utility board lawyer questions whether payments should be front-loaded

NB Power might need to be more aggressive in paying off deferred costs from the refurbishment of its Point LepreauNuclear Generating Station, the New Brunswick Energy and Utilities Board heardMonday.

The hearings, which began just as the trouble-plagued Lepreau reactor shut down for the third time since restarting last year, is considering how NB Power should pay for just over $1 billion in regular costs the utility deferred during its refurbishmentfrom March 2008 to November 2012.

A man in a dark suit is speaking.
NB Power vice-president Darren Murphy says the utility wants to pay back the $1 billion in expenses it deferred during the Point Lepreau refurbishment with equal monthly payments over 27 years. (CBC)
The utility wants to pay the amount, much like a home mortgage, in equal monthly instalments over 27years.But EUB lawyer Ellen Desmond questioned whether that puts too much faith in the plant's prospects for trouble-free operation.

"Isn't it fair to say that as we move out intothe future, we have less certainty around the life of theplant in terms of how long the asset will actuallycontinue to operate?" asked Desmond to a panel of NB Power executives.

But NB Power says it is equally likely Lepreau could perform better than expected over time andpaying its costs gradually prevents current customers from paying too much for something that will also benefit future customers.

"I agree there would be some uncertainty, but it could be both favourable or unfavourable," saidJonathan Dobson, NB Power's director of enterprise risk and treasury management in advocating for lower monthly payments on Lepreau..

"It provides forstability and predictability, and is a fair approach toallocate it amongcustomers over the life of the plant."

Most of the deferred expense comes from the utility's need to replace power whileLepreau, which is its largest source of generation, was offline during a 54-month longreconstruction.The utility relied more heavily on its other generators during that time and imported power from neighbouring utilities to make up the difference.

NB Power told theEUBhearing in Fredericton that it would like to repay the deferred costs over more than 300 equal monthly payments of $5.6 million. In the first year that lowers the principal owed on the deferral account by $1.6 million a month, or about $20-million in the first year.Desmond asked if more aggressive payments on the principal in early years wouldn't guard against thereactor not performing as well as expected, which it hasn't so far.

"If the Board was concerned about the outstandingliability, and the event that perhaps Point Lepreau was tostop working earlier than expected, would you agree thatreduces that risk?" asked Desmond.

Dobson agreed, but suggested that concern is unwarranted and could force the utility to raise rates for current customers unnecessarily.

Desmond asked how the reactor was currently performing.

"Actually, currently the Lepreau is out for astation outage," replied NB Power vice president Darren Murphy.

On Friday, crews powered Lepreau down to deal with the latest in a series of problems toplaguethe reactor since restarting last November.One of four steam lines that turn the station's giant turbine malfunctioned last spring and is being repaired over the next twoweeks.The plant suffered other slowdowns, including when the chemistry of the water in the plant's boilers was found to be too corrosive shortly after restart and later when plugs in the end of the reactor's new fuelchannelsbecame stuck and couldn't be removed to allow for refuelling.

Those and some other minor issues severely cut Lepreau's production during its first 11 months, but NB Power has publicly vowed following the latest fix thatthe plant will operate at 100 per centcapacity through the winter until a planned shutdown next spring.