3 Muskrat Falls contractors file court action to block release of pay info - Action News
Home WebMail Saturday, November 23, 2024, 04:39 AM | Calgary | -12.0°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
NL

3 Muskrat Falls contractors file court action to block release of pay info

Three senior managers working on the Muskrat Falls hydro megaproject are going to Supreme Court to keep the public from knowing how much they are paid information the provincial government says should be released.

They say disclosure would cause them undue financial harm

Nalcor Energy agreed to release the details of contractor compensation for the Lower Churchill power project, but some of those contractors objected. Now they want their day in court. (CBC)

Three senior managers working on the Muskrat Falls hydro megaproject are going to court to keep the public from knowing how much they are paid information the provincial government says should be released.

In documents filed at Newfoundland and Labrador Supreme Court last month, the contractors said disclosing that information would be an "unreasonable invasion" of personal privacy.

The three managers Paul Harrington, the Lower Churchill project director for generation; business services manager Lance Clarke; and project controls manager Tanya Power have not been hired as employees of Nalcor Energy, but instead as contractors through the consulting companies that they own.

They declined comment, through their lawyer.

In court documents, they saydisclosing their names and the names of their companies, along with other details of their contracts with Nalcor, "would not serve the public interest" and would cause them "undue financial harm."

Those court filings came in response to access-to-information requests by CBC News.

According to Nalcor, contractors in two other Muskrat Falls management roles did not go directly to court to stop the release of pay details, but instead complained to the province's privacy commissioner.

Six others did not object to the financial information being released.

The Muskrat Falls spillway and intake on the Churchill River, near Happy Valley-Goose Bay, is pictured in this file photo. Three contractors on the hydro megaproject have gone to Supreme Court to block the release of information related to their pay. (Nalcor Energy)

In a statement to CBCNews, Nalcor confirmed it is not paying the legal fees for these contractors in relation to these matters.

The energy corporation said it will make submissions to the privacy commissioner and the court which support its position that the information can be disclosed under the access-to-information law.

Change in law governing Nalcor

The province's Liberal government vowed changes to enhance transparency at Nalcor last year, in the wake of critical media reports by The Telegram and CBC News.

At the time, Premier Dwight Ball said secrecy related to the compensation for contractors didn't pass his "smell test."

Later that fall, the province's privacy commissioner foundthe law governing Nalcor trumped access-to-information legislation. That decision put those pay details for contractors off-limits to the public.

In response, Ball said the law would change.

Newfoundland and Labrador Premier Dwight Ball said last September that Nalcor Energy's refusal to disclose the rates it pays contractors for the Muskrat Falls hydroelectric project didn't pass his "smell test." The province later amended the law to permit the release of such information. (Todd O'Brien/CBC)

"This is a Crown corporation; this is public funds," Ball told reporters in early December.

"And I think the people of this province would have a right to know, they have a right to know, how their money is being spent."

Six months later, the Liberal government proceeded with those legislative changes.

"It is neither necessary nor appropriate to keep the cost of these independent contractors secret from the public," Natural Resources Minister Siobhan Coady told the legislaturein late May.

After those amendments passed, CBC News re-filed requests for contractor compensation that had previously been redacted.

Nalcor agreed to release the information.

But three of those requests resulted in applications to Supreme Court, for judicial review of the decision.