Dawson City plans new water treatment plant - Action News
Home WebMail Saturday, November 23, 2024, 12:15 PM | Calgary | -12.1°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
North

Dawson City plans new water treatment plant

The existing plant was built nearly 40 years ago, and the Yukon government says it's no longer adequate.

Existing plant is nearly 40 years old, and no longer adequate

The existing water treatment plant in Dawson City was built in the late 1970s. A new plant will cost between $15 million and $20 million. (Town of Dawson City)

Dawson City's drinking water infrastructure is getting some major upgrades, with plans fora new treatment plant and a larger reservoir.

The existing plant was built nearly 40 years ago, and the Yukongovernment says it's no longer adequate.The town wasordered by the governmentto improve how water is processed and treated.

John Skilnyk, Dawson's chief administrative officer, says the water is safe to drink right nowbut the current infrastructure needs to be replaced.

"This is a result of total coliform[bacteria] hits that we were finding in the water,"he said."Although they are not worrisome at this point, they are often a precursor to cryptosporidium or giardia."

Skilnyksays water samples are taken and analysed twice a week.

"We have to be on this all the time and we are ... we are monitoring the water, and we are always trying to ensure that the residents of Dawson get the best water."

New wells

Three years ago, the town constructed four new wells. Under territorial drinking water regulationspassed in 2007, the well watermust be treated.

The wells are known as "ground water under direct influence" (GWUDI) wells,because water from the nearby Yukon River can get into the source water. That makes the wellsvulnerable to contamination by pathogens.

Plans for the new water treatment facility are now before the Yukon Environmental and Socio-economic Assessment Board (YESAB), and open for public comment.

The plan is to build the facilityin two stages, starting next summer, with the completion set for2020.The townalso plans to build a larger water reservoir afterthe new plant is built.

The project is estimated to cost between $15 million and$20 million.