$89M for Halifax Water's new Burnside building is 'excessive,' says provincial regulator - Action News
Home WebMail Friday, November 22, 2024, 07:28 PM | Calgary | -11.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Nova Scotia

$89M for Halifax Water's new Burnside building is 'excessive,' says provincial regulator

According to an evaluation by the Nova Scotia Utility and Review Board, the price tag isn't justifiable.

Price not justifiable, according the Nova Scotia Utility and Review Board

A rendering of a large gray building.
This rendering shows the proposed design of a building that would consolidate operations of four existing Halifax Water depots at a single site on Jennett Avenue in Burnside. (Halifax Water)

The proposed $89-million price tag for a new Halifax Water operations centre in Burnsideis not justified, according to anevaluationcarried out for the Nova Scotia Utility and Review Board.

The regulator sought a second opinion after the project's budget jumped from $52 millionin April 2023 to $89 million by November 2023 a $37 million or 71 per cent increase.

The estimate has since been pared back slightly to $87 million. Thebuilding size was enlarged by 14 per cent from the original approval.

"It is our recommendation that the current funding request does not get approved until further design, scope, and budget validation are completed," said real estate services firm CBRE,which conducted the review.

Its38-page report was posted this week by the board.

'Integrated' approach to construction

Halifax Water wants to move staff fromfour sites across the Halifax Regional Municipality into a single operations depot on Jennett Avenue in Burnside.

The estimated cost soared after the utility decided to use what's known as integrated project delivery (IPD), a method where construction costs and profits for project participants are agreed upon up front in a single contract. The owner, general contractor and others all collaborate to ensure those goals are met.

Experts told Halifax Water this approach would reduce risks experienced in the recent construction market due to labour shortages and supply chain issues.

CBRE said team members working on the project Bird-Chandos Joint Venture, Group2 Architecture, FBM, CBCLand Atlantica Mechanical Contractors areexperienced and highly regarded and should stay to complete the next phases of the project.

"That said, with the unclear reasoning for the building increase in size and the unrealistic budget cost increase, it would be recommended more realistic targets be set," CBRE said.

"It is recommended that the IPD contract be reviewed by a contract specialist to ensure Halifax Water understands their obligations, risks, and full understanding of the costs."

Approach questioned

CBREsays the current budget contains "excessive" contingencies.For instance, eightper cent budgeted for construction riskshould be cut to threeper cent, it said.

The consultant also questioned whether the integrated contractlivesup to its billing.

"The IPD contract notes the owner is obligated to pay for the cost of the work even if it exceeds the target costs. This statement seems to defeat the purpose of the IPD approach," CBRE said.

Halifax Water declined to address specific points raised by theCBRE.

Halifax Water statement

"Halifax Water recognizes that this is a significant investment, and we are committed to acting in the best interest of our customers," spokesperson Jeff Myrick said in a statement to CBC News.

"We are reviewing the consultant's report and working with them and the board to address questions or concerns."

Construction of the operations depot isexpected to start this summer and take 24 months to complete.