Finishing LRT trains by Sunday 'entirely achievable,' rail director says - Action News
Home WebMail Friday, November 22, 2024, 10:33 AM | Calgary | -10.8°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

Finishing LRT trains by Sunday 'entirely achievable,' rail director says

Having all of Ottawa's LRT vehicles in working order by Sunday is "entirely achievable," according to the city's rail director even though the system hasn't yet been tested at full capacity.

RTG has yet to run all 15 coupled trains at once

O Train
Alstom is supposed to have all trains for the Confederation Line in working order by Sunday, July 7. (City of Ottawa)

Having all of Ottawa's LRT vehicles in working order by Sunday is "entirely achievable," according to the city's rail director even though the system hasn't yet been tested at full capacity.

Last month, Mayor Jim Watson hauled executives fromRideau Transit Group (RTG),the consortium building the 12.5-kilometre Confederation Line, and train maker Alstominto his boardroom to express his frustration that the major infrastructure project is more than a year late.

At the time, Alstom CEO Henri Poupart-Lafarge, who flew in from France for the meeting, promised that the trains would be completed and working by July 7 this Sunday.

Meeting that deadline is supposed to set the stage forRTG handing over the LRTsystem to the city by mid-August.

Henri Poupart-Lafarge, CEO of French company Alstom, told Mayor Jim Watson last month that the trains could be completed by July 7. (Kate Porter/CBC)

Work progressing

According to Michael Morgan, the director of the city's rail office, work on the trains has been progressing.

It's been going quite well. I think that at this point it appears that it's entirely achievable.- Michael Morgan, City of Ottawa rail director

The city's next official update on the project will be presented at Wednesday's finance and economic and development committee, but Morgan said last week he's optimistic even though RTG hasn't yet operated 15 coupled trains at once.

That number is significant because during rush hour, 15 coupled trains, each consisting of two light rail vehicles, will be in service. An extratwo coupled trains will be on hand as backups.

"There's still some time left before July 7," said Morgan late last week. "It's been goingquite well. I think that at this point itappears that it's entirely achievable."

One month ago, city council heard the trains were "not ready for prime time."Thetrains continued to experience problems with their doors and brake valves, which are time-consuming to retrofit and modify.

Michael Morgan, Ottawa's director of rail, said he thinks July 7 is 'entirely achievable.' (CBC)

The city requires an updated report that shows all modifications have been completed, and "we also want to see the 15 double trains on the line," Morgan said. "Those are they two high-level things that we want to seefor them to demonstrate that they have met that July 7deadline."

RTG was able to runnine coupled trains and five singles on the track on Thursday,according to Morgan the largest numberthus far to run at once.

However, it's not clear how long those trains were able to operate, or whether they are able to run along the entire length of track.

Of course, train movement is affected by issues other than the trains themselves. For example, last week, parts of the track were affected by "sun kinks," when the rail bends due toprolonged exposure to high heat, Morgan confirmed.

Trains were stopped in one area of the track on Friday, and repairs to the kinked rail were planned for this weekend.

Two of the Alstom trains are seen at Tunney's Pasture station. (Chris Rands/CBC)

Alstom moving production to Toronto area

In the meantime, Alstomrecently told RTGit's moving its train production from the Belfast Yard in Ottawa to Brampton, Ont., northwest of Toronto.Alstom has a contract with the provincial transit agency Metrolinx to provide light rail trains for Toronto-area LRTsystems.

The France-based company is building not only the34 LRTvehicles for the first stage of the Confederation Line, but an additional 38 for the future expansion of the east-west transit route.

So far, Alstom has assembled nine of the Stage 2 trains at Belfast Yard. The company said in a statement toCBC that it plans to build a total of 13 trains in Ottawa, which should be accomplished by November. The remaining trains will be built at the Brampton plantand transported back to Ottawa.

A company spokesperson told CBC that Alstom's "permanent workforce" in Ottawa will continue to have jobs in the cityor be transferred to Brampton. Other "hired staff" who are not permanent will likely lose their jobs by November.

Morgan said he wasn't concerned aboutAlstomtalent leaving town because the company is part of the 30-year LRT maintenance deal the city has with RTG.