Cost of Ottawa's latest LRT delay climbing into millions

As city councillors absorb the news that Ottawa's LRT launch is delayed yet again, they're also asking how much the setback is going to cost and who's going to pay.

City treasurer preparing detailed report on financial consequences of setback

The city treasurer's office is working on a detailed report about the costs of delaying the LRT. (CBC)

As city councillorsabsorb the news that Ottawa's LRTlaunch is delayed yet again, they're also asking how much the setback is going to cost and who's going to pay.

The short answer is, we just don't knowyet.But the final tally willcertainly totalmillions, and it's not at all clear who's going topick up the tab.

During Monday's finance committee meeting, Coun. Diane Deans asked city treasurer Marian Simulik to prepare a detailed report on the financial consequences of the Rideau Transit Group's (RTG) failure to meetthe Nov. 2 deadline.

That report isn'texpected until the end of the month.

But we've been here before: In February, the city announced RTGwouldn't make the original May 24 deadline to hand the Confederation Line keys over to the city, and three months later Simulikissued a detailed report on the financial impact.

Here, invery broad strokes, is what the latest delay could cost us.

Coun. Diane Deans asked the city treasurer to prepare a report detailing the financial consequences of the latest LRT delay. (CBC)

OC Transpo budget blown

One thing we know for sure is that OC Transpohas blown its operational budget for 2018.

The city had budgeted $411.6 million for transit operations in 2018, $5million less than it actually spent the previous year. But even as early as May, the treasurer reportedOC Transpo'soperating costs were expected to increase by $21.9 million.

Those costs rose mainly because OC Transpo was forced to continue bus service it had planned to end when LRT whichis supposed to be cheaper to operate came online, and thanks to the loss of additional fare revenue from the expected bump in ridership LRT was supposed to bring.

That was all assumingpassengers would be riding LRTby the end of November, which is no longer the case.

Transit expenses could reach $20M

From the Maynumbers, wecan extrapolate ever so generally the sorts of cost increases we can expect. The original delay was about five months. From that, we can estimate the monthly additional costs from the delay to total about $4.4 million.

The city and RTG haven't agreed on a new deadline, but at Monday's meetingwe heard that the independent experts advising the city's rail team believe we could be riding the Confederation Line in February.

If we assume anotherthree months of delay; that could cost OC Transpo$13.2 million in additional operational fees.

Bus detours caused by LRT construction cost the city about $2 million a month. (Kate Porter/CBC)

Separately, keeping the bus detours going costs a little more than$2 million per month. So that's another $6 million in costs the city will have to incur.

Then there's the suggestion that transit fares be frozen instead of increasing by 2.5 per cent on Jan. 1, 2019, as planned. That's another $250,000 per month.

Add it all up, and taxpayers are staring at a potential bill of $20 million.

Savings to offset some costs

Of course, the city will also earn some money because ofthe delay.

First, there's the $1-million penaltyRTGwill have to pay for missing Nov. 2.

The city is also delaying handing over$262 million in payments it owes to RTG when the job is finally finished, which will delay debt payments. Nor will the city be spending money on maintenance or electricity fees for the light rail system during the delay.

OC Transpo's renamed Route 11 was one of 24 routes changed on Sept. 1 in advance of LRT. Three councillors are now lobbying to reinstate the old route. (CBC)

The great unknowns

A number of possible costsremain unknown.

OC Transpogave 345 bus drivers pink slips at the start of August. They were only expected to work until Dec. 1. Are they available to work an additional three months? Will the city have to pay the drivers a premium to get them to stay on? Amalgamated Transit Union Local 279, which represents OC Transpodrivers, did not return CBC's requests for an interview.

And nowcouncillors are calling for the restoration of at least some of the 24 bus routes that were changed on Sept. 2 in anticipation of LRT. Changing bus routes is a complex business, and it's unclear whether OC Transpowill cave to political pressure. But even reinstating a few routes will cost money.

Finally, while the city insistsRTGis on the hook for any costs caused by a delay, including the additional $2 millionfor bus detours,the two sides aren't always in agreement about where the responsibility for the delay lies.

Case in point: the Rideau sinkhole.Neither RTGnor the city will take responsibility forcausing the crater,and just who'll pay for what is still under discussion.

The final cost of this latest delay to taxpayers may not be tallied for some time.