OC Transpo will get 100 fewer electric buses for $1B price tag - Action News
Home WebMail Tuesday, November 26, 2024, 04:04 AM | Calgary | -17.0°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

OC Transpo will get 100 fewer electric buses for $1B price tag

The business case and funding for OC Transpo's big shift to electric buses have been updated, and nowthe City of Ottawa expects to get 350 buses instead of 450 for the previously announced billion-dollar price tag.

$350M federal grant and $380M loan will help city shift away from diesel

A photo of a new electric OC Transpo bus sits in a garage during a photo op Nov. 26, 2021.
A new electric OC Transpo bus sits in a garage during a photo op Nov. 26, 2021. (Frdric Pepin/Radio-Canada)

UPDATE | City council voted Jan. 25to go over the spending proposal further attransit commission.


The business case and funding for OC Transpo's big shift to electric buses havebeen updated, and now the City of Ottawa expects to get 350 buses instead of 450 for the previously announced billion-dollar price tag.

After originally exploring onlya small pilot project, OC Transpomade a majorturn in June 2021 and staked its future on a quick transition away from adiesel-poweredfleet. City councilresolved to buy only zero-emission buses a move that would also tackle one of the municipality'slargest sources of greenhouse gas emissions.

At the time, the city was presented with the sudden promise of federal funding, and madeplans to buy 450 zero-emissionelectric buses by 2027 for $986 million.

At a news conference at an OC Transpo garage last week after funding was secured, however, federal officials announced they would help pay for 350 buses.

Richard Holder, the City of Ottawa's director of engineering services, explained that was what thecity could afford given the funding it was allocatedand the shorter timeframe of the federal Zero-Emission Transit Fund, with projects eligible to March 2026. It's possible that fund could be extended andthe city might be able totap into it again, he noted.

Until then, however, a report beforecity council on Wednesday now pegs the total cost of 350 buses at$974 million: $653 million on the buses,$214million for charging infrastructure, but also"transition costs" of $107 million that are almost five times higher than the estimates a year and a half ago.

Holder said in an emailed statement that transitional services "include new tools and equipment, required training and program management, and essential facilities upgrades, such as structural upgrades and a new parking facility over exterior parking"although notelectrical upgrades.

City receives big loan and grant

Transit commission chair Coun. Glen Gower said he expects a fluctuation in costs in any major procurement. The City of Ottawa received a smaller share of federal funding than it originally expected, he explained,after Infrastructure Canada decided it would help more cities with the transition to electric buses.

Still, he points out the federal funding bridgesthe gap between the cost of a diesel bus and the higher cost of electric ones, making it possible for the city to afford to replace its fleet with the zero-emission alternative.

"It's not every day that the city isin the receipt of $350 million from the federal government. I mean that's a significant investment," said Gower."I think it's also a reminder that we have so much attention on LRT, but a significant portion of our transit system is still buses and will be buses for the foreseeable future."

The City of Ottawa received approval in December from Infrastructure Canada to receivethe maximum $350 million grant under its Zero-Emission Transit Fund.

Last summer, city council also approved taking out a loan of up to$380 million with the Canada Infrastructure Bank that can be repaid with the savings it expects from fuel and maintenance.

Between those two sources, plus the $348 million the city intended to spend on diesel bus replacements anyway, city staff say the e-buses will be cost neutral.

Fewer buses purchased in early years

The City of Ottawa intends to start out slow when it comes to getting the electric buses into service:

  • 26 in 2024.
  • 77 in 2025.
  • 110 in 2026.
  • 137 in late 2026.

It was auditor general Nathalie Gougeonwhorecommended the city not be overly ambitious with its first purchase. Shehas been doing anunusual set ofproactive audits of the electric bus planbecause she was concerned about the cost,new technology and speed with which the city took it on.

After one of those audits, the City of Ottawa decided to partner with the Toronto Transit Commission on the procurement of the buses, rather than putting out a request for proposals of its own. Gougeonhad foundOttawa's own draft RFPwasn't specific enough about technical details.

OC Transpocurrently has a fleet of 855 buses, made up of predominantly 40-foot and 60-foot diesel buses along with 151 double-deckers. At the moment, only four buses in the fleet are electric.

A politician at a desk with his nameplate uses a computer mouse.
Barrhaven West Coun. David Hill, seen here late last year, put forward a motion Wednesday to defer the electric bus procurement plan to transit commission. (Giacomo Panico/CBC)

Will go to transit commission first

City staff had urged council to give them the go-ahead Wednesday to start spending the money, but councillorsinstead voted 20-5 to send the file to transit commission for greater scrutiny.

The referral motion from Barrhaven West Coun. David Hillcited the report that came out of last year's inquiry into Ottawa's problem-plagued LRT line including the need for councilto "exercise meaningful oversight of critical decisions made by city staff."

Sending the electric bus spending plan to transit commission first, Hill said,would allowcouncillors to question city experts, and members of the public could share their thoughts.

"We're not two months out of the LRT inquiry, and we're about to embark on the next phase of a significant investment in our transit technology," he told council.

"I have concerns that, certainly, I would like to ... have the opportunity to address, so that I can look at residents in the eye and tell them that I did everything I could to rebuild their trust."

Transit commission is next set to meetFeb. 9, although several councillors floated the idea of calling a special meeting before then.

A table of names, listing how they voted on a motion.
Ottawa city councillors voted 20-5 to send the spending plan to transit commission for more discussion. (Kate Porter/CBC)

With files from Trevor Pritchard