Final Trillium Line test timeline coming Thursday - Action News
Home WebMail Friday, November 22, 2024, 07:21 PM | Calgary | -11.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

Final Trillium Line test timeline coming Thursday

The City of Ottawa says it will share when final testing of its north-south Trillium light rail line will begin. It has said these kinds of tests should take at least three weeks and are not the final step before opening.

Afternoon update expected on trial runs, which will take at least 3 weeks

A photo of the Trillium Line on Carleton University campus at night.
A Trillium Line train passes through the Carleton University campus on a test run in September 2024. (Kate Porter/CBC)

The City of Ottawa says it will sharewhen final testing of its north-southTrillium Line will begin.

It has called media to aThursday afternoon briefing "on the status of trial running of O-Train Lines 2 and 4, including the anticipated start date."

The light rail lineswill run diesel trains betweenBayviewandLimebank stations (Line 2) and between South Keys and Airport stations (Line 4). Bayview connects to the east-west Confederation Line LRT.

The previous, shorter version of the north-south rail line closed in the spring of 2020.The plan was to reopen with expanded service in August 2022, but there have been several delays getting it built and ready.

In July, city officials shared some of what the two steps of trial running will involve: a14-day reliability testing period; and aseven-day phase simulating various "failure scenarios" such asan immobilized train, a failed rail switch or a medical emergency on board.

The trial running period required in contracts will mean greater monitoring and reporting than testing done in the past, officials said.

OC Transpo's goal is 98.5 per cent reliability during the trial and leadership has said they'll test until they reach it, which could take more than those 21 days.

The agencywould then have to go to Transport Canada to get regulatory approval to operate.

Richard Holder, the city'sengineering director turned rail construction director, said in Augustonce trial running begins, it will take another four to six weeks before passenger service can start.

The nearly $5 billion rail transit expansionis also extending tracks east to Trim Road and west to Algonquin College and Moodie Drive.

The most recent target for opening the eastern expansion was the summer of 2025. The western extension could open in late 2026 or early 2027.