Most new TTC streetcars to be taken out of service to fix 'welding problem'

Many of the new streetcars delivered to Toronto significantly past deadline by Bombardier will be taken out of service and sent to Quebec to fix a "welding problem," the TTC says.

Fixing 67 flawed streetcars will take till 2022, but TTC foresees no disruption in service

A red streetcar driving on the street.
Despite repeated setbacks, Bombardier has promised to deliver all 204 of the new streetcars to the TTC by end of 2019. (Doug Ives/Canadian Press)

Many of the newstreetcars delivered to Toronto significantly past deadline by Bombardier will be taken out of service and sent to Quebec to fix a "welding problem," the TTC said Wednesday.

Sixty-seven streetcars need to be fixed, according to Toronto Transit Commission spokesperson Brad Ross. To date, Bombardier has delivered 89 cars of a 204-car, $1-billion order originally placed in 2009.

The problem with the streetcars isnot a safety issue, Ross said, but rather a welding irregularity that will affect the cars' guaranteed service life of 30 years.

Crews at Bombardier will need to strip the cars down to their frames and reweld the problem areas, a process that is expected to take as many as 19 weeks per car.

Three to four streetcars at a time will be sent to Bombardier's plant La Pocatire, Que., for repair.Ross said TTCriders won't see a "disruption in service" during the work, which could take until 2022 to complete.

You can listen to Metro Morning's full interview with Ross in the clip below.

Bombardier notified the TTCof the problems with the cars in October 2017, according to Ross. The transportation manufacturing giant will cover the additional costs of the repairs, he added, or else the TTC will seek compensation.

Toronto's mayor feeling 'extreme frustration' with streetcar issues

In a statement, Toronto Mayor John Tory said TTC executives are working closely with Bombardier to ensure the work goes smoothly.

"I have made no secret about my extreme frustration with this streetcar deal that was signed by a previous city council back in 2009 and Bombardier's slow progress in actually delivering the vehicles bought and paid for by Toronto taxpayers," Tory said.

"TTC CEO Rick Leary is working with Bombardier to ensure these repairs will have little to no impact on our service, and we have been assured this will not affect the delivery of new streetcars."

All 204 of the new streetcars are scheduled to be delivered by the end of 2019.In October 2015, the TTC board voted to sue the company over multipleproduction and delivery delays.

Bombardier has since added a second production line in Kingston, Ont., to ensure upcoming deadlines are met.